Leading the £4.3m Conservation of Kendal Parish Church

Leading the £4.3m Conservation of Kendal Parish Church

With more than £3.1m of National Lottery Heritage Fund support secured, a long-planned programme of conservation and improvement at Grade I-listed Kendal Parish Church can now progress.

Having worked with Kendal Parish Church since 2020, John Coward Architects is now acting as lead consultant, contract administrator and conservation architect for the £4.3m conservation programme. We were appointed to lead the architectural work in February 2025 and have since developed the project through RIBA Stage 3.

The National Lottery Heritage Fund award will support urgent intervention to the fifteenth-century tower and Bellingham Chapel roof, alongside changes to heating, access, and the use of parts of the interior.

So far, much of our role has been establishing why the historic fabric is failing before deciding how best to respond.

Working with the wider conservation team, we have carried out a forensic investigation of the tower and Bellingham Chapel. This has included structural and timber surveys, building environmental monitoring, photogrammetry, and ongoing material trials. That evidence has allowed us to develop the design with a much clearer understanding of the risks involved.

The tower has suffered from chronic damp and water ingress for many years. Moisture is affecting the masonry, internal wall linings and timber structures, while earlier piecemeal attempts to address the problem have not resolved it.

One of the main challenges will be allowing the structure to dry and reinstating the ways in which its masonry was originally designed to deal with rainwater.

Medieval masons designed details such as drip courses, string courses, buttress caps, and window hood moulds to shed water from the walls, but many have eroded over time. Our proposals include repairing or replacing these features, filling voids within the wall cores and introducing a lime-based surface treatment.

Trial panels have been in place for more than a year, allowing us to monitor how the proposed materials cure. The results are helping determine both the final specification and how much time to allow for application and curing during construction.

The Bellingham Chapel presents a different set of problems. Its lead roof covering is in very poor condition and is allowing water into the building. Temporary measures have been needed within the roof space to collect water, and investigations have also identified decay in parts of the timber structure and problems due to insufficient ventilation.

The covering will be completely replaced and re-detailed to improve rainwater discharge and ventilation, alongside repairs to the roof structure and associated masonry.

The plans also extend into the church interior. Pews will be removed from the outer north and south aisles to create more flexible spaces, and the raised pew platforms will be replaced with level stone floors incorporating underfloor heating.

Exploratory investigations below those floors have been particularly revealing. During the process, we encountered disarticulated human remains within the floor voids — perhaps not surprising in a building on a site with around a thousand years of history, but something that called for careful handling.

We worked closely with the Diocese and the project archaeologist during those investigations. The new floor construction has been designed specifically to avoid disturbing known burials and scattered human remains below ground.

The underfloor heating will form part of a wider reworking of the church’s heating system. The infrastructure is being designed so that an air source heat pump can be introduced in future, with planning approval for the external unit already in place.

Kendal Parish Church intends to remain open throughout construction. That will make the early phases, particularly the pew removal and floor lowering, more complex, but we also see value in allowing people to witness conservation in progress.

Visitors will be kept safely separated from active areas, while the programme gives them opportunities to see and understand what is happening to the building around them.

Reaching this stage is significant. The church’s condition has created difficult problems for many years, and the funding now allows a comprehensive response to move forward.

Over winter and spring 2026/27, we will develop the scheme through RIBA Stage 4, drafting detailed construction drawings and specifications before tendering to suitable contractors. Construction is currently expected to begin in August 2027, with the programme continuing into 2029.

We also hope what we learn from the tower will be useful beyond the project. If the approach performs as intended, it could help inform the treatment of other historic churches confronting similar problems with masonry, moisture and earlier inappropriate interventions.

The wider professional team includes Clach Conservation Engineering on structural engineering and masonry; Morham and Brotchie as quantity surveyor and cost consultant; Hutton and Rostron on building pathology and environmental monitoring; John Book on the heating system; and The Creative Core on exhibition and interpretation