Repairing the Tower at St John’s, Workington
A £708,310 grant from the Places of Worship Renewal Fund means long-planned repairs can now go ahead at Grade II* listed St John’s Church, where we have been monitoring problems with the stone tower since 2018.
We were first appointed at St John’s in 2018. Since then, Mike Darwell has carried out two quinquennial inspections, both of which identified significant deterioration in the tower masonry.
The present stone tower dates from 1844–47 and replaced an earlier timber tower. It is finely detailed externally, with cornices, hood moulds and pilasters beneath a lead-covered domed roof.
Much of that projecting stonework is held together by iron cramps and ties embedded within the masonry.
Mike explains:
“Due to Workington’s coastal location, the tower gets hammered by some of the worst weather Cumbria can throw at it.
“Over time, the exposed cornices, hood moulds and other water-shedding surfaces have eroded, and joints between the stones have deteriorated. Moisture finds its way into the masonry and eventually reaches the ironwork embedded within it.
“As the iron corrodes, it expands and starts to fracture the surrounding stone. Once that happens, everything opens up further, more moisture gets in, and the process accelerates.”
We developed a comprehensive repair programme for the tower in 2020 and took the scheme to tender, but the required capital funding was not available at the time.
The condition continued to deteriorate. Pieces of stone began to fall from the tower, and the church erected temporary scaffolding as a safety measure.
That scaffold also gave us an opportunity we hadn’t had before: to inspect the face of the tower up close.
In April this year, Mike carried out a tactile survey of the accessible external masonry. It identified fractured stonework, open joints, and widespread evidence of damage from corrosion of the embedded iron cramps and ties.
“When we got up close to the tower, it was clear that the scaffold couldn’t simply come down,” Mike said. “At least some holding repair work was going to be needed, and that in itself was going to be expensive.”
The timing of the new Places of Worship Renewal Fund has therefore been particularly important for St John’s. The church has been awarded £708,310, allowing the much-needed tower repairs to move forward, with work expected to begin later in 2026 and continue into the first half of 2027.
St John’s itself was built in 1821–23 under the 1818 Church Building Act and is an unusual building in Cumbria. Sir Ninian Comper reordered its interior in 1931, and his work included the gilded baldacchino over the altar.
“It’s a glorious church,” Mike said. “It has a rich and fascinating history, and we’ve known for a long time that the tower needed substantial work. The grant has arrived at a key point.”
We are working closely with structural engineers WML Consulting, with cost advice provided by Saunders Quantity Surveyors.
Recent posts
-
A wet, windy day in the Upper Duddon Valley brought us together with our clients at the University of Leeds and colleagues from the National…
-
A £708,310 grant from the Places of Worship Renewal Fund means long-planned repairs can now go ahead at Grade II* listed St John’s Church, where…
-
A mixed day of sunshine and showers took Mike Darwell from the bells and clock in the tower to the roofs, rainwater goods, masonry and…